2006 |
Project |
Client |
Project/Owner |
m |
Type |
Completion |
| Natural Gas Pipeline and Metering Station Project for RPCL (Ratchaburi) |
Kikuchi Industry (Thailand) |
PTT |
328 |
24" Steel Pipe |
19-Feb-07 |
| Natural Gas Pipeline and Metering Station Project for RPCL (Ratchaburi) |
Kikuchi Industry (Thailand) |
PTT |
300 |
24" Steel Pipe |
14-Feb-07 |
| Ptt Ngv Gas Pipeline Project Thai Oil Station and Sahapat Station |
ITD |
PTT |
342 |
6" Steel Pipe |
29-Jan-07 |
| Natural Gas Pipeline and Metering Station Project for RPCL (Ratchaburi) |
Kikuchi Industry (Thailand) |
PTT |
84 |
24"Steel Pipe |
20-Jan-07 |
| Natural Gas Pipeline and Metering Station Project for RPCL (Ratchaburi) |
Kikuchi Industry (Thailand) |
PTT |
100 |
24"Steel Pipe |
26-Dec-07 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
70 |
4 x 125 mm. HDPE |
13-Dec-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
110 |
6 x 125 mm. HDPE |
08-Dec-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
105 |
4 x 125 mm. HDPE |
02-Dec-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
110 |
4 x 125 mm. HDPE |
01-Dec-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
125 |
6 x 125 mm. HDPE |
30-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
97 |
4 x 125 mm. HDPE |
27-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
120 |
4 x 125 mm. HDPE |
24-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
95 |
4 x 125 mm. HDPE |
20-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
120 |
4 x 125 mm. HDPE |
17-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
97 |
4 x 125 mm. HDPE |
14-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
100 |
4 x 125 mm. HDPE |
11-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
200 |
6 x 125 mm. HDPE |
08-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
146 |
6 x 125 mm. HDPE |
04-Nov-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
265 |
6 x 125 mm. HDPE |
28-Oct-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
97 |
6 x 125 mm. HDPE |
20-Oct-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
240 |
6 x 125 mm. HDPE |
13-Oct-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
190 |
6 x 125 mm. HDPE |
12-Oct-06 |
| Rojana Rayong Industraial Estate |
Kikuchi Industry (Thailand) |
PTT |
410 |
4" Steel Pipe |
18-Oct-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
230 |
6 x 125 mm. HDPE |
06-Oct-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
327 |
6 x 125 mm. HDPE |
29-Sep-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
150 |
6 x 125 mm. HDPE |
27-Sep-06 |
| Conduit Installation Along Kanchanapisak |
Vorapat Engineering |
TOT |
145 |
6 x 125 mm. HDPE |
15-Sep-06 |
| Natural Gas Distribution Pipeline Project for Thai Air and Ngv Station |
TRC Construction |
PTT |
630 |
4” Steel Pipe |
14-Sep-06 |
| Mab Ta Put Industrial Estate-Rayong |
Kikuchi Industry (Thailand) |
PTT |
42 |
4” Steel Pipe |
11-Sep-06 |
| Mab Ta Put Industrial Estate-Rayong |
Kikuchi Industry (Thailand) |
PTT |
36 |
4” Steel Pipe |
11-Sep-06 |
| Natural Gas Distribution Pipeline Project for Thai Air and Ngv Station |
TRC Construction |
PTT |
635 |
4” Steel Pipe |
09-Sep-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess |
450 |
16" Steel Pipe ,+4" |
07-Sep-06 |
| Natural Gas Pipeline Project for vehicle ptt ngv Mother Station at Bv#5 |
TRC Construction |
PTT |
61 |
6” Steel Pipe |
06-Sep-06 |
| Natural Gas Distribution Pipeline Project for Thai Air and Ngv Station |
TRC Construction |
PTT |
175 |
4” Steel Pipe |
02-Sep-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
984 |
6” Steel Pipe |
17-Aug-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
1100 |
6” Steel Pipe |
11-Aug-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
85 |
6” Steel Pipe |
08-Aug-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
60 |
6” Steel Pipe |
22-Jul-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
SPM Consultants & Service |
Gulf Electric |
310 |
450 mm. HDPE |
15-Jun-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
SPM Consultants & Service |
Gulf Electric |
170 |
630 mm. HDPE |
10-Jun-06 |
| PPT Natural Gas Distribution Pipeline Project |
ITD |
TGI |
110 |
6” Steel Pipe |
07-Jun-06 |
| PPT Natural Gas Distribution Pipeline Project |
ITD |
TGI |
441 |
6” Steel Pipe |
29-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
85 |
4” Steel Pipe |
29-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
15 |
4” Steel Pipe |
27-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
72 |
4” Steel Pipe |
26-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
72 |
4” Steel Pipe |
25-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
66 |
4” Steel Pipe |
24-May-06 |
| PPT Natural Gas Distribution Pipeline Project |
ITD |
TGI |
285 |
6” Steel Pipe |
23-May-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
24 |
4” Steel Pipe |
22-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
72 |
4” Steel Pipe |
19-May-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
650 |
6” Steel Pipe |
17-May-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
72 |
6” Steel Pipe |
17-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
60 |
4” Steel Pipe |
15-May-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
60 |
4” Steel Pipe |
15-May-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
796 |
6” Steel Pipe |
14-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
48 |
4” Steel Pipe |
13-May-06 |
| Phu Horm Gas Development Project |
Mc Connell Dowell |
Amerada Hess (Thailand) |
24 |
4” Steel Pipe |
12-May-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
439 |
6” Steel Pipe |
12-May-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
SPM Consultants & Service |
Gulf Electric |
200 |
710 mm. HDPE |
11-May-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
665 |
6” Steel Pipe |
10-May-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
48 |
4” Steel Pipe |
09-May-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
108 |
6” Steel Pipe |
06-May-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
580 |
6” Steel Pipe |
05-May-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
36 |
4” Steel Pipe |
28-Apr-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
320 |
6” Steel Pipe |
26-Apr-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
1050 |
6” Steel Pipe |
25-Apr-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
48 |
4” Steel Pipe |
23-Apr-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
724 |
6” Steel Pipe |
22-Apr-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
531 |
6” Steel Pipe |
20-Apr-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
245 |
6” Steel Pipe |
11-Apr-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
262 |
6” Steel Pipe |
08-Apr-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
905 |
6” Steel Pipe |
05-Apr-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
48 |
4” Steel Pipe |
05-Apr-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
1040 |
6” Steel Pipe |
01-Apr-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
JFE Engineering |
Gulf Electric |
343 |
18” HDPE |
29-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
24 |
4” Steel Pipe |
28-Mar-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
628 |
6” Steel Pipe |
28-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
60 |
4” Steel Pipe |
26-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
48 |
4” Steel Pipe |
24-Mar-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
585 |
6” Steel Pipe |
23-Mar-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
970 |
6” Steel Pipe |
19-Mar-06 |
| AOT Sub Station |
D.B.T.Engineering |
ITO |
104 |
125mm.HDPE |
18-Mar-06 |
| AOT Sub Station |
D.B.T.Engineering |
ITO |
82 |
125mm.HDPE |
17-Mar-06 |
| PPT Natural Gas Distribution Pipeline Project |
Italian-Thai Development |
TGI |
175 |
6” Steel Pipe |
16-Mar-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
JFE Engineering |
Gulf Electric |
260 |
18” HDPE |
13-Mar-06 |
| PTT Natural Gas Distribution |
Polytechnology |
PTT |
250 |
10” Steel Pipe |
10-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
60 |
4” Steel Pipe |
07-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
36 |
4” Steel Pipe |
06-Mar-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
660 |
6” Steel Pipe |
05-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
24 |
4” Steel Pipe |
05-Mar-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
36 |
4” Steel Pipe |
04-Mar-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
552 |
6” Steel Pipe |
04-Mar-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
JFE Engineering |
Gulf Electric |
230 |
18” HDPE |
01-Mar-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
835 |
6” Steel Pipe |
28-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
66 |
6” Steel Pipe |
25-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
102 |
6” Steel Pipe |
25-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
72 |
6” Steel Pipe |
23-Feb-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
24 |
4” Steel Pipe |
13-Feb-06 |
| Wang Noi Kaeng Khoi Pipeline Project |
Coleman Tunnelling (IRL) |
PTT |
48 |
4” Steel Pipe |
13-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
1060 |
6” Steel Pipe |
13-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
950 |
6” Steel Pipe |
03-Feb-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
634 |
6” Steel Pipe |
30-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
836 |
6” Steel Pipe |
28-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
890 |
6” Steel Pipe |
25-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
600 |
6” Steel Pipe |
21-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
843 |
6” Steel Pipe |
19-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
80 |
6” Steel Pipe |
18-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
595 |
6” Steel Pipe |
17-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
620 |
6” Steel Pipe |
16-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
72 |
6” Steel Pipe |
14-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
100 |
6” Steel Pipe |
13-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
65 |
6” Steel Pipe |
12-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
65 |
6” Steel Pipe |
11-Jan-06 |
| Sai Noi-North/South Bangkok Power Plants Gas Pipeline Project |
NACAP Asia Pacific (Thailand) |
PTT |
95 |
6” Steel Pipe |
10-Jan-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
JFE Engineering |
Gulf Electric |
33 |
18” HDPE |
05-Jan-06 |
| Water Discharge Pipeline KK2 Power Plant Project |
JFE Engineering |
Gulf Electric |
30 |
18” HDPE |
07-Jan-06 |