Method Statement for Horizontal
Directional Drilling
Introduction:
Each horizontal directional
drilling job site has it’s own unique characteristics.
The following method statement is intended to indicate the
typical activities at a job site. For a particular job or
crossing, prospective clients should contact Strega and
request a method statement for their requirements.
The schedule of activities
can normally be broken down into the following parts:
1. SITE SURVEY AND BORE PLANNING
2. PREPARATION OF SITE
3. HDD DRILLING OPERATION
4. LEAVING THE SITE
5. DOCUMENTATION
1. SITE SURVEY AND BORE PLANNING
A survey team will map out the bore paths. Their function
is to provide an accurate plan and elevation of the area
that the pipeline will go through. The survey team will
also locate, identify and mark any buried services that
run close to the path of the bore.
With the data provided by
the surveyors, the locator operator or drilling manager will
make a bore plan and profile using the Atlas bore planning
computer software. The bore plan will establish the entrance
and exit angles and the radius of the pipe curvature, to achieve
the depth and length of the drill. The bore plan will also
show any utilities that were found by the survey team and
will allow for the necessary deviation of the pipeline to
avoid contact with the utility.
When the bore plan is completed
it will be presented to the client or his representative for
approval. Upon approval of the bore plan the HDD operations
can proceed.
2.
PREPARATION OF SITE
An all weather access to the entrance and exit sites for the
HDD operations must be constructed and a level hard standing
area for the drilling equipment prepared at each of these
sites as follows:
a) Exit or rig side
A rectangular area has to be prepared that is approximately
10 metres long by approximately 5 metres wide.
Access to the entrance should be an all weather road capable
of withstanding heavily loaded transporters. The hard stand
should be either clay filling with a cover of laterite, wooden
mats or steel plates.
The clean water (not salt-water) requirements should be met
by either a reliable pumped supply or by water trucks. If
it is determined that the water supply is not sufficient to
meet the needs of a crossing, water storage tanks will be
used to store enough water to meet the requirement.
Pits will be excavated at the pipeline exit and entry points.
The pits are to contain the borehole slurry. They must be
of sufficient capacity to accommodate the used slurry/cuttings
mixture. Further disposal of the used bentonite during the
operation must be possible using other means and should be
arrange for together with the client
b) Entrance side
The hard stand should be constructed in a similar manner to
the exit. A similar access, as constructed for the exit should
be provided. A slurry pit will be constructed to collect any
bentonite/slurry discharged from the drill hole.
3. HDD DRILLING OPERATION
The survey team will place stakes at the pipeline exit
and entry points. The directional drilling unit is placed
at the exit where the drill will enter at exactly the correct
location. The drill unit is then elevated at the rear so that
the entrance angle conforms to the drill profile drawing.
The rig is then anchored in position. If necessary a 20 tonne
excavator will also be used as an anchor for the drill rig.
The drilling operation begins
by drilling a pilot hole using the drill bit, the drill head
and the pressure injection of drilling fluid. The drilling
is carried out continuously in intervals of 4.5 metres, equivalent
to one length of drill pipe. Location of the drill bit is
monitored using the DCI locating system. An electronic transmitter
in the drill head sends information to the locator operator’s
receiver. As each drill rod is drilled into the ground the
locator operator takes a reading from his equipment and informs
the drill operator of the location, pitch and roll of the
drill head. From this information the operator knows the location
of the drill head at all times. The operator uses the information
to maintain the preplanned path of the bore. The accuracy
of the drilling is verified by comparing the coordinates of
the actual location of the drill bit against the planned drill
profile. If there is a major difference between the actual
and planned location of the drill bit, the operator is able
to correct the actual profile by pulling back to a correct
position of the planned profile and begin re-drilling.
Once the drill bit exits the other end of the drill hole,
the drill head is removed and a reamer is attached to the
drill string. Depending on the diameter of the pipe to be
installed, several reamings with progressively larger diameter
reamers may be necessary (i.e. with a 24 inch diameter pipe,
the first reaming could be with an 16 inch reamer, the second
reaming with a 24 inch reamer and the third reaming with a
32 inch reamer). During the reaming process, drilling fluid
is pumped under pressure through the drill string to the reamer.
As the drill rig pulls the reamer back, drill pipe is attached
continuously behind the reamer for the subsequent reaming
and pipe pulling operations.
When the bore hole has been reamed out to the correct diameter
the back reamer is sent back down the bore one or two more
times to ensure that the hole is clear of any large objects
and that the slurry in the hole is well mixed.
This prepares the hole for the pipe to be pulled in. Once
the driller is satisfied that the hole is clear and ready
for the pipe, the pull head is connected to the drill string
via a swivel. The swivel prevents the client’s pipe
from rotation during the pullback.
Prior to the pull back, the client’s pipe, which has
had a pull head welded on to it, has been prepared and hydrostatically
tested by the client in a single length. The length being
equivalent to or greater than the length of the drilled hole.
The client’s pipe is then pull back toward the exit
area by the drill rig.
4. LEAVING THE SITE
The site will be left clean and tidy and basically in a similar
condition as it was prior to the drilling commencing.
5. DOCUMENTATION
Upon completions of the HDD crossing Strega will produce an
as built drawing using CAD, which will be presented to the
client.
For additional information,
comments, or questions, please contact
Strega |