Our third pilot hole using the ParaTrack II guidance system has been completed.
The crossings involve drilling parallel to and across an existing 42" steel gas pipeline. Because of the close proximately to the existng pipeline and the depth of the pilot hole, traditional walkover guidance would have struggled to locate the drill path. The ParaTrack II effortlessly completed the pilot holes without incident. |
| FOR MORE INFORMATION :
|
|
| January 30, 2007 |
|
We have completed our first crossing using ParaTrack II. Strega would
like to thank John Teer and Ruud van Haren of Prime Horizontal for their
assistance in getting us up and running with the ParaTrack guidance system. |
| FOR MORE INFORMATION :
|
|
| January 18, 2007 |
|
Strega is pleased to announce that we have taken delivery of a new
Vermeer D80 x 100 Series II. This machine is to replace the company's
older first generation D80 x 100.
|
| FOR MORE INFORMATION :
|
|
| January 30, 2007 |
|
Strega welcomes Mr. Bundit Sucharitchandra as the company's new
operations manager. Mr. Bundit brings with him a wealth of construction
industry experience.
|
| FOR MORE INFORMATION :
|
|
2006 |
| December 27, 2006 |
|
Strega is pleased to announce that we have taken delivery of a new
ParaTrack II HDD guidance system. The ParaTrack II compliments and
enhances Strega's guidance capabilities. This new system will allow
Strega to complete jobs that were previously considered to be difficult
or impossible to complete using traditional walkover locating systems.
Between the ParaTrack II and the DCI Eclipse systems Strega now has the
ability to complete a wide variety of crossing. |
| FOR MORE INFORMATION :
|
|
| August 30, 2006
|
|
The company has just completed it largest
contract to date. Between August 2005 and August 2006 Strega installed a
total of 25,124 metres of 6 inch steel fiber optic conduit on the Sai
Noi North/South Bangkok power plant pipeline project. Strega was
subcontracted to Nacap Asia Pacific to complete the FOC HDD works. "It
has been a good project for us" says John Barton, Managing Director of
Strega. "This project has set a number of accomplishments for the
company. Our longest crossing of 1,100 metres was achieved on this job
using our Vermeer D80, a 40 tonne machine, something that quite a few
people said would be impossible. By paying attention to a number of
factors we were able to easily do over 1,000 metres at four locations."
|
| FOR MORE INFORMATION :
|
|
| August 15, 2006
|
|
We have been published!...
for details see:
www.nodig-construction.com
or click here to download a PDF copy of the publication.
and
www.trenchlessaustralasia.com
or click here to download a PDF copy of the publication.
|
| FOR MORE INFORMATION :
|
|
| June 27, 2006
|
|
Ground breaking ceremony. Today Strega
celebrated the new office and workshop facilities ground breaking
ceremony. The first pile for the workshop was driven at precisely 09:11.
The 288 square metre office and 432 square metre workshop is scheduled
to be completed at the end of November 2006.
|
| FOR MORE INFORMATION :
|
|
| March 29, 2006
|
|
Strega have just completed their first
major HDD rock project. The project involved the installation of a 350
metre long 450 mm HDPE pipe through 100 MPa rock.
|
| FOR MORE INFORMATION :
|
|
| 28 January, 2006
|

|
Strega have just taken delivery of
their latest HDD rig, an American Augers DD140B drill with a American
Augers MP 400 mud system.
The DD140B was purchased specifically to
complete a river crossing through rock in central Thailand. |
| FOR MORE INFORMATION :
|
|
2005 |
| 2/03/05 |
|
Strega was recently awarded a contract to install two 24 inch and one 12
inch steel fuel pipes under the new Suvarnabhumi Airport runways. Each
24 inch pipe will have a length of approximately 66 metres and the 12
inch will be approximately 32 metres long. Due to concerns of damage to
the new runways Strega has elected to use pipe ramming instead of HDD as
the method to install the two pipes. A 16 inch and 5 3/4 inch Hammerhead
mole will be used to install the pipes.
|
| FOR MORE INFORMATION :
|
|
| 1/02/05 |
|
Strega have moved to new offices. Please note our new address and contact numbers are now:
Strega Company Limited
61/13-14 Moo6, Lamlukka Road
Bung-kam-proi, Lamlukka
Patumthani 12150,
THAILAND
Tel: (662) 987 9552-4
Fax: (662) 987 9556
|
| FOR MORE INFORMATION :
|
|
2004 |
| 16/07/04 |
 |
Strega has
been awarded a small works contract by Nacap Drilling.
The project will involve the installation of a
bundled 8 inch steel pipe and 6 inch HDPE pipe. |
| FOR MORE INFORMATION
:
|
|
| 10/07/04 |
 |
Strega purchases
new drill. Due to the increased work load of upcoming
projects Strega today took delivery of a
used Vermeer D50 x 100. The drill is expected to
be used on projects involving crossings with lengths
of up to 580 metres and diameters of up to 18 inches. |
| FOR MORE INFORMATION
:
|
|
| 2/07/04 |
 |
Strega is pleased
to announce that it has been award the main directional
drilling contract for the Thappline Suvarnabhumi
Airport Dedicated Line Project. The main contractor,
ITD-NSC Joint Venture awarded the contract on 1st
of July 2004. The contract will involve the installation
of over 3,000 metres of 18 inch steel fuel pipe.
|
| FOR MORE INFORMATION
:
|
|
| 15/05/04 |
 |
Strega has
just been awarded the contract for the installation
of over 9,500 metres of four inch steel pipe
in Chachoengsao, Thailand. The contract specifies that
the entire project must be completed using directional
drilling. The directional drilling works must be
completed with in 60 days of starting the on site
works.
|
| FOR MORE INFORMATION
:
|
|
2003 |
| 10/10/03 |
 |
To increase
the directional drilling locating capabilities,
Strega has just taken delivery of the new DCI SST
locating system. The new system uses a wireline
to send the the drillhead information to the drill
operator. Unlike older systems, SST system does
not need the locater operator to be directly above
the drillhead to receive information from the transmitter.
With the new SST Strega now has the capability
to complete difficult crossings such as roads and
wide rivers with better accuracy and confidence.
|
| FOR MORE INFORMATION
:
|
|
2002 |
| 17/05/02 |
 |
Strega has
purchased a Vermeer D16 x 20a directional boring
machine to expand its capability for smaller jobs.
The D16 x 20a NAVIGATOR is a powerful, small machine.
It will allow Strega to more easily drill in small,
congested spaces, such as across busy roads and
highways in the city.
“Three years ago, we
started out as a big drill contractor, but we are
now expanding our range to provide greater service
to our customers. The D16 allows us to do some
of the smaller, shorter work for our customers
that we couldn’t do physically or cost-effectively
with a large drill,” says
John Barton, Managing Director. |